MRT Flyover Lane Enters Girder Installation
access_time August 11 2016 01:43 PM remove_red_eye 2678
Reported by Nani Suherni | Translated by Rizky Mawardi
Reported by Nani Suherni | Translated by Rizky Mawardi
Mass Rapid Transit (MRT) flyover lane corridor at Jalan Sisingamaraja enter the girder installation. Girder installation target completion from Jalan Sisingamaraja heading to Haji Nawi is by the mid of 2017.
Daily target is six girders. Working hour is from 10 PM to 4 AM
PT MRT Jakarta Director, Dono Bustami, said the installation is part of MRT flyover lane construction.
“Daily target is six girders. Working hour is from 10 PM to 4 AM,” he said, Wednesday (8/10).
Second-Phase MRT Project Completed This YearBox girder to be installed is produced by Wika Beton-Jaya Beton Joint Operation. CP 103 package contract is handled by Obayashi-Shimizu-Jaya Konstruksi Joint Venture (OSJ JV).
“Girder installation at CP 103 has two launching gantry devices that will be used for route Jalan Sisingamaraja up to Jalan Fatmawati,” he closed.